Question No : 1
Which meeting should the Scrum Master attend (not facilitate)?
正解:
Explanation:
Scrum Master should attend Scrum of scrums as participant, rest Iteration review and DSU is facilitated by SM.
Question No : 2
What are two typical anti-patterns with Product Owners (POs)? (Choose two.)
正解:
Explanation:
The antipatterns are:
Question No : 3
Which two events explicitly implement the Lean-Agile Mindset of relentless improvement? (Choose two.)
正解:
Explanation:
Relentless improvement can be best drived by Iteration Retrospective and Inspect and adapt event.
Question No : 4
Which statement is true about scrum?
正解:
Explanation:
Scrum is a FRAMEWORK which is best suitable for Team.
Question No : 5
Systems builders and Customers have a high level of responsibility and should take great care to ensure that any investment in new Solutions will deliver what benefit?
正解:
Explanation:
Enterprises decide to embrace Lean-Agile development either because their existing processes aren’t producing the results they need, or because they anticipate that they won’t in the future. By choosing a Lean-Agile path, they’re embracing a model based on incremental development and early and continuous value delivery. Continous value delivery will create ability to deliver early and often has a direct economic benefit.
Question No : 6
What is a recommended Story-splitting technique for Agile Teams?
正解:
Explanation:
Agile teams often use 'estimating poker,' which combines expert opinion, analogy, and disaggregation to create quick but reliable estimates. Disaggregation refers to splitting a story or features into smaller, easier to estimate pieces. And firstly Implement the 'happy path' and the rest of the scenarios afterwards.
Question No : 7
Achieving the goals of Release on Demand requires an understanding of how to decouple what?
正解:
Explanation:
Achieving the goals of Release on Demand requires an understanding of how to decouple the release from deployment.
Question No : 8
Why are big Stories considered an anti-pattern?
正解:
Explanation:
Bug Stories are difficult to complete in one iteration.
Question No : 9
What is one way Kanbans are used in SAFe?
正解:
Explanation:
Kanban systems are the primary mechanism to achieve SAFe Principle #6 C Visualize and limit WIP, reduce batch sizes, and manage queue length.
Question No : 10
When is iteration planning completed?
正解:
Explanation:
teration planning is ideally done with the entire team in a meeting, including key stakeholders, typically lasting one to a few hours, at the beginning of an iteration. This ensures that the entire team understands what needs to be done, and they commites the plan.
Question No : 11
An organization is conducting their first Program Increment Planning session, and the new teams are asked to provide their capacity.
Which action is part of the initial capacity planning process?
正解:
Explanation:
For one iteration One team member's capacity is 8, and if any holiday or trainings are there then we have to deduct 1 day from each team members capacity.
Question No : 12
Who participates in the Inspect and Adapt event?
正解:
Explanation:
All ART stakeholders participate along with the Agile Teams in the I&A event. The result is a set of improvement backlog items that go into the Program Backlog for the next PI Planning event. In this way, every Agile Release Train (ART) improves every PI.
Question No : 13
What does transparency mean in a scrum environment?
正解:
Explanation:
Transparency means clear and transparent current process and updates should be visible to everyone.
Question No : 14
What is the main reason why some teams never reach Stage 4 (Performing) in the stages of high performing teams?
正解:
Explanation:
Sometimes Team needs proper guidance and support if it lacks team may not reach that phase.
Question No : 15
What happens to improvement items identified during the Iteration Retrospective?
正解:
Explanation:
When issues have been identified, root cause analysis is performed, potential corrective actions are discussed, and improvement Stories are entered into the Team Backlog.