Question No : 1
In the Schedule Production app, which settings can you make in the planning strategy? Note: There are 3 correct answers to this question.

正解:

Question No : 2
When working with both cross-plant and plant-specific material statuses in the mater al master, which status has the highest priority?

正解:

Question No : 3
You want to schedule an operation finitely, without moving other operations .
Which scheduling strategy do you select?

正解:

Question No : 4
What is the purpose of a reporting point confirmation in repetitive manufacturing? Note:
There are 2 correct answers to this question.

正解:

Question No : 5
Duringproduction order creation, several valid production versions are found .
How does the system choose the product conversion?

正解:

Question No : 6
You want to create a production order from a planned order .
What methods could you use?
Note: There are 2 correct answers to this question.

正解:

Question No : 7
Advanced Planning uses master data and transaction data from SAP S/4HANA In which data obje can you set the advanced planning flag? Note: There are 2 correct answers to this question.

正解:

Question No : 8
You want to set up a make-to-order planning scenario for a finished material. Some components from the bill of materials (BOM) should be procured per sales order, other components should be procured for various requirements. Fore casting is NOT possible .
Which settings do you make to achieve this?

正解:

Question No : 9
You have maintained the parameters for simple discontinuation the material master of a component .
Which business process will be affected if the available stock is zero and the discontinuation date is in the past?

正解:

Question No : 10
Which materials have a negative quantity in a bill of materials or in a recipe? Note: There are 3 correct answers to this question.

正解:

Question No : 11
Your quality department detects a deviation in a raw material batch. Unfortunately, this batch has already been used in production .
How can you identify all affected finished goods stocks?

正解:

Question No : 12
Why would you use phantom assemblies? Note: There are 3 correct answers to this question.

正解:

Question No : 13
Mode selection is one of the scheduling options available in Advanced Planning in SAP S/4HANA. When can you use mode selection?
A. When multiple planned orders exists in one resource
B. When alternate resourcesare used within one operation
C. When multiple production versions are maintained for one product
D. When multiple operations are maintained for one product

正解: B

Question No : 14
In your plant, MRP is activated .
Which options do you have to exclude a material from the MRP run? Note: There are 2 correct answers to this question.

正解:

Question No : 15
Which actions does the system perform by default when you save a confirmation for a finished product in repetitive manufacturing? Note: There are 3 correct answers to this question.

正解: